GRID-FORMING CONTROLS

Grid-forming controls for energy storage

Fractal EMS turns grid-forming inverters into a grid-forming plant. We coordinate PCS, batteries and the point of interconnection so the site rides through disturbances, and when the grid is lost, we island, black start and resynchronize, safely and in compliance.

Grid following vs. grid forming

Lead the grid. Don't follow it.

Nearly every operating battery and solar inverter is grid following: it measures the grid and injects current in step with it. A grid-forming inverter behaves like a synchronous generator. It sets its own voltage and frequency, resists change instantly, and can run as the only source in an island.

Grid following

Measures the grid, then reacts

Response: measure, then react, about 100–200 ms
No native inertia; limited fault current
On weak grids it can oscillate, trip or be curtailed
Cannot hold the grid up, and cannot run without one.
Grid forming

Sets its own voltage and frequency

Response in about 10 ms, with synthetic (virtual) inertia
Contributes fault current within inverter limits
Stable on weak grids, and strengthens the grid for neighbors
Islanding and black start become possible, with EMS coordination.

Why grid forming, why now

Spinning generation is retiring

Coal and gas units provide inertia and system strength by spinning. As they retire, frequency moves faster and grid-following plants struggle to stay connected when the grid needs them most.

Weak grids limit interconnection

The best renewable sites are often at the edge of the network, where low short-circuit strength makes grid-following plants unstable or forces curtailment. Grid forming lets plants connect and operate there.

Grid events are moving regulators

The 2025 Iberian blackout and India's 2026 Khavda disturbance put system stability at the top of the agenda. On Oʻahu, a grid-forming battery helped avoid rolling blackouts after large generator trips in 2024.

New revenue for stability

Great Britain's stability contracts, Germany's inertia market and Australia's system-strength contracts now pay grid-forming batteries for services that once came only from spinning machines.

Grid forming is going global

Required in seven markets. The EU is next.

In under two years, grid forming has moved from voluntary specifications to a hard requirement for new storage, and to a tender condition in four more markets. RfG 2.0 is set to apply it across all 27 EU member states.

World map of grid-forming requirements for energy storage by market
MarketStatusRequirementTiming
MISO
U.S. Midwest
RequiredGrid-forming controls for standalone BESS in the interconnection queueFrom the 2023 queue cycle
Finland
Fingrid
RequiredGrid-forming for grid storage of 10 MW or moreIn force since Mar 2025
MexicoRequiredGrid-connected storage must use grid-forming technologyEffective Apr 2026
GermanyRequiredNew transmission-connected BESS; paid inertia market for GFM assets2026
PortugalRequiredTransmission-connected or 45 MW and above: grid forming plus synthetic inertiaConnection requests from Oct 2026
ChileRequiredAll storage and the storage portion of hybrids; stable island operationEntering operation from Aug 2026
India
CEA
RequiredBESS of 50 MW or more: grid forming, black start and AGCFrom Apr 2027
ERCOT
Texas
Grid support requiredAdvanced grid support (grid-forming-like) for inverter-based storage on the transmission grid; incentive proposed for existing plantsInterconnection agreements signed from Apr 2026
Brazil · Hawaii · S. Korea · Saudi ArabiaIn tendersGrid forming specified in battery auctions, utility RFPs and procurements2019–2027
European Union
RfG 2.0
ComingMandatory for storage of 1 MW or more across all member statesAdoption targeted Q4 2026
Great Britain · AustraliaComingPaid stability / system-strength contracts; mandates proposed2027+

Status as of November 2026. Summary of public information from grid operators and regulators; not legal advice.

Next wave: standards catch up

NERC already recommends grid forming for all new BESS on the bulk power system. IEEE is developing P2800.1, a recommended grid-forming practice, plus a grid-forming amendment to IEEE 2800, and DOE's UNIFI grid-forming specifications are now at Version 3.

Next wave: solar and wind

Fingrid now requires grid-forming support for new type D wind and solar connecting where the short-circuit ratio falls below 1.0, and India's draft rules would require grid forming for a share of new solar and wind inverters. The hybrid plant controller becomes central to compliance.

The PCS forms the grid. Fractal EMS makes it work.

Grid forming is primarily a function of the PCS: it creates the voltage waveform and delivers the instant response. But a plant is dozens of inverters, batteries, breakers, transformers and a point of interconnection that must act as one. As NERC puts it, grid-forming and black-start-capable are not the same thing. Grid forming is the prerequisite; the rest is plant design and controls, and that is where Fractal EMS comes in.

Fractal EMS

The plant brain
Plant P/Q setpoints
Plant and unit limits (P, Q, S, ramp, GSU)
SOC balancing across the fleet
Islanding, black start and resync
Market dispatch, telemetry and HMI

Grid-forming PCS

Forms the grid
Voltage and phase reference
Virtual inertia response
Frequency and voltage droop
Real-time current limiting
Voltage and frequency ride-through

BMS

Protects the cells
Live charge/discharge limits
Cell-level protection
Thermal management and balancing
Insulation and fire-safety signals
P/Q setpoints and mode commands ↓↑ Telemetry and live charge/discharge limits

Black start and islanding, sequenced

Eight steps from grid loss to grid return

When the grid is lost, the difference between a controlled island and a second outage is sequencing. Fractal EMS orchestrates every step.

GRID CONNECTEDGrid connected. The plant follows dispatch at the point of interconnection. STEP 1 · DETECTGrid lost. Ride-through alarm received; Fractal EMS confirms the site has islanded. STEP 2 · PROTECTHold the plant. POI breaker open. Thermal and aux loads held; SOC and readiness confirmed. STEP 3 · FORMBlack start. The lead grid-forming inverter black starts and ramps voltage on the plant bus. STEP 4 · VERIFYIsland stable. Frequency and voltage in range, for example 60.0 ± 0.3 Hz. STEP 5 · BUILDAdd inverters. Other inverters come online in stages to limit inrush. STEP 6 · SERVEPick up load. Load is picked up in controlled blocks within SOC limits. STEP 7 · RESYNCGrid returns. Sync-check confirms voltage, frequency and phase match. STEP 8 · RETURNBack to dispatch. The POI breaker closes and normal dispatch resumes. UTILITY GRID GRID LOST V · f · phase ✓ 52 POI BREAKER+ sync-check relay PLANT BUS 60.0 Hz ✓ LEAD UNIT 2 UNIT 3 LOADS AUX / THERMAL grid-forming PCS + BESS FRACTAL EMS SITE CONTROLLERcontrol · telemetry · sequencing 1 · DETECT 2 · PROTECT 3 · FORM 4 · VERIFY 5 · BUILD 6 · SERVE 7 · RESYNC 8 · RETURN

Grid forming is not a checkbox on an inverter datasheet

It is a plant-wide behavior that has to be studied, sequenced, tested and operated. Fractal provides everything a grid-forming plant needs above the inverter, from the system studies to the equipment, the software and decades of service.

Future-proof for mandates

Meet ERCOT, MISO, Fingrid, CEA and upcoming EU requirements, and be ready for new stability markets.

Hardware-agnostic GFM integration

Proven with grid-forming PCS from multiple OEMs, including seamless GFM/GFL transitions.

Model-verified compliance

Inertia, droops and current limits modeled in PSSE, PSCAD and DIgSILENT, then tuned at commissioning.

Local control that keeps running

No cloud dependency: islanding, black start and resync execute even if the WAN is lost.

Revenue stacking in GFM mode

Keep virtual inertia while dispatching frequency response, voltage support and arbitrage.

Battery-aware protection

Live BMS limits, SOC clamps and fleet-wide SOC balancing protect batteries and warranties.

Utility, TSO and ISO integration

DNP3, IEC 61850, Modbus TCP, OPC UA and ICCP, with secure IPsec VPN.

Every grid event captured

A 50-samples-per-second historian for event analysis, model validation and warranty claims.

Grid forming in the field

Been there. Done that.

Grid forming matters most on weak grids. From transmission-connected plants and utility microgrids to isolated networks, off-grid industry and black start testing, Fractal EMS coordinates grid-forming events.

6Grid-forming projects completed
2More in execution
3Continents
18+ GWhIn operations
Finland
50 MW / 100 MWh

Transmission-scale BESS

Every PCS power module runs in grid-forming mode on a 110 kV network, contributing virtual inertia, voltage and frequency support and short-circuit current, while the plant still earns market revenue.

Wisconsin
400 kW / 3.2 MWh

Community microgrid

When the village's single distribution line goes down, the battery islands and keeps the village powered for up to eight hours.

California
2 MW / 4 MWh

Off-grid industrial microgrid

The battery runs only in grid-forming mode as the backbone of an off-grid microgrid for a 450,000 sq. ft. facility, with fuel cells and solar.

Texas
2 × 4.2 MVA PCS

Black start test bed

Ahead of a utility-scale deployment: black start, form a 34.5 kV island, energize test units in stages and resynchronize to the utility.

Queensland
1 MW / 2 MWh

Isolated utility network

A standalone grid-forming battery works with the town's power station to support local solar and reduce reliance on diesel.

Queensland
850 kW PV + 1 MWh

Remote solar-diesel network

A new solar farm and battery halve diesel use, saving about 150,000 litres a year; on sunny, low-load days the town runs on solar and battery.

One platform, every layer

Fractal EMS HMI on two monitors showing plant trends and fleet status

One controls platform for every grid-forming plant

Any DC block, any PCS, any inverter
Controls stay on site, with no cloud dependency
Cybersecure, domestic supply chain
One platform across your whole fleet
Commissioning and COD testing by our operators
Backed by our 24/7 NERC CIP Medium ROC

One stop shop

We design, supply, program, integrate and commission the whole scope, from grid-forming studies to black start testing, with a single point of accountability for the entire controls scope.

EMS / PPC
SCADA
RTAC programming
Master plant controls
Networking
Cybersecurity
Network enclosures
Commissioning
Training
24/7 NERC CIP Medium ROC
Fractal EMS control racks
Grid forming in your next interconnection agreement? Talk to our sales engineers.
Request a proposal